Action Plan for July 24, 2009 Flooding on Vanstone

The Action Plan presented to the Environment Committee on May 17 includes a number of projects costing $32.1 million in total in Table 1 - Recommend Action Plan.  The plan calls for spending $6.8 million in 2011 and $23 plus million in 2012with $2.2 million spent in 2010.

The Action Plan includes work in Katimavik-Hazeldean centres on upgrades to the Vanstone Ditch and Sewer at a preliminary estimate of  2011 design costing $200,000 and actual work in 2012 costing $2,000,000

The Consolidated Report Report attached to the formal statement to  presented to the Environment Committee sets out the explanation of the alterations to roadside ditches at pages 12 and 13 in report  item .6